We will perform a Horner EZY 3 Tank Tightness Test as follows:
- Product levels in tank are measured
- Testing equipment is installed
- Supply and return lines are closed as close to the tank as possible
- Vent and fill lines are plugged
- Test is performed and completed
- Testing equipment and plugs are removed, and valves are restored to original positions
Lastly, a copy of the test report will be sent to NYC Department of Environmental Conservation.